Executive summary
- Forecast finish moves from 26 Jan 2024 to 12 Feb 2024, 17 days later, because See First Patient in New Addition (HXP1710) finished 17 days later. That work is on the driving path, so it moves the end date.
- Finish Carpentry and Millwork (HXP1730) finished 17 days later and Finishes Complete (HXP1770) finished 17 days later, but those activities are off the driving path, so they do not explain the finish.